Part of the Sino Iron Project located approximately 25km south of Cape Preston in the Pilbara region of North West, Western Australia, the Scope of Work under this contract includes the provision of the upstream lining of the Western and Northern walls of the Tailings Storage Facility Stage 2 of Cell 1B, previously constructed by BGC Contracting in March 2016.

With a targeted construction program of 4 months, the scope for this project consists of the:

  • Construction of clayey bedding layer and the installation of geosynthetic liners along the northern and western flanks of the Stage 1B TSF and the raising of the existing decant tower.
  • Construction of the Eastern Access Road and Related Infrastructure including the Pipe Servitude Ramp, Stormwater Retention Embankments along the Eastern Access Road, and North-Eastern Stormwater Diversion Channel and Bund.
  • Production of sheeting material for road surface.

Client: CITIC Pacific Mining

Duration:
November 2016 - February 2017
Status:
Completed
Location:
Western Australia