Boddington Project

At the completion of the contract, the BGC fleet moved a total volume of 16.5 million BCM of material.

The Boddington Mine is a gold and copper mine located approximately 130km South East of Perth. The mine is estimated to have a 20 year life and will produce more than 1,000,000 ounces of gold per year.

PRESTRIP MINING PROJECT

BGC was contracted to complete the prestrip mining for the gold mine. The scope of work included clear and grub, contract mining, topsoil and gravel stripping, and contract drainage work. At peak capacity BGC was operating 5 mining fleets, 1 scraper fleet, 1 clear and grub fleet, and 1 drainage fleet. At peak, the group was managing an onsite workforce of approximately 200 personnel.

At the completion of the contract, the BGC fleet moved a total volume of 16.5 million BCM of material.

Client: BGC Management Company Pty Ltd

Status:
Completed
Location:
Western Australia
Value:
$60 million